Building construction wage rates — Los Angeles, California
135 classifications published for building construction in Los Angeles, from one general wage determination. Base rate and fringe are printed exactly as the determination publishes them; base plus fringe is the only figure calculated here.
CA20260022 — modification 5
Reproduced from General Decision CA20260022, modification 5, published 2026-08-06 by the U.S. Department of Labor. Read the same determination on SAM.gov.
CA20260022 modification 5 prints 135 classifications in its rate tables, transcribed here as published. The loaded rate is the published base rate plus the published fringe; nothing else is calculated.
Reproduced from General Decision CA20260022, modification 5, published 2026-08-06 by the U.S. Department of Labor. Read the same determination at https://sam.gov/wage-determination/CA20260022/5.
ASBESTOS WORKERS/INSULATOR (INCLUDES THE APPLICATION OF ALL INSULATING MATERIALS, PROTECTIVE COVERINGS, COATINGS, AND FINISHES TO ALL TYPES OF MECHANICAL SYSTEMS)
- Base rate
- $56.32
- Fringe
- $26.52
- Base + fringe
- $82.84
ASBE0005-002 · Union rate · effective 2024-07-01
FIRE STOP TECHNICIAN (APPLICATION OF FIRESTOPPING MATERIALS FOR WALL OPENINGS AND PENETRATIONS IN WALLS, FLOORS, CEILINGS AND CURTAIN WALLS)
- Base rate
- $39.94
- Fringe
- $20.65
- Base + fringe
- $60.59
ASBE0005-002 · Union rate · effective 2024-09-01
ASBESTOS REMOVAL WORKER/HAZARDOUS MATERIAL HANDLER (INCLUDES PREPARATION, WETTING, STRIPPING, REMOVAL, SCRAPPING, VACUUMING, BAGGING AND DISPOSING OF ALL INSULATION MATERIALS FROM MECHANICAL SYSTEMS, WHETHER THEY CONTAIN ASBESTOS OR NOT)
- Base rate
- $23.52
- Fringe
- $13.37
- Base + fringe
- $36.89
ASBE0005-004 · Union rate · effective 2022-07-04
BOILERMAKER
- Base rate
- $51.98
- Fringe
- $42.11
- Base + fringe
- $94.09
BOIL0092-003 · Union rate · effective 2024-01-01
BRICKLAYER; MARBLE SETTER *THE WAGE SCALE FOR PREVAILING WAGE PROJECTS PERFORMED IN BLYTHE, CHINA LAKE, DEATH VALLEY, FORT IRWIN, TWENTY-NINE PALMS, NEEDLES AND 1-15 CORRIDOR (BARSTOW TO THE NEVADA STATE LINE) WILL BE THREE DOLLARS ($3.00) ABOVE THE STANDARD SAN BERNARDINO/RIVERSIDE COUNTY HOURLY WAGE RATE
- Base rate
- $45.53
- Fringe
- $20.29
- Base + fringe
- $65.82
BRCA0004-007 · Union rate · effective 2024-05-01
MARBLE FINISHER
- Base rate
- $43.38
- Fringe
- $15.36
- Base + fringe
- $58.74
BRCA0018-004 · Union rate · effective 2024-06-01
TILE FINISHER
- Base rate
- $37.96
- Fringe
- $13.77
- Base + fringe
- $51.73
BRCA0018-004 · Union rate · effective 2024-06-01
TILE LAYER
- Base rate
- $51.82
- Fringe
- $19.32
- Base + fringe
- $71.14
BRCA0018-004 · Union rate · effective 2024-06-01
TERRAZZO FINISHER
- Base rate
- $42.11
- Fringe
- $14.67
- Base + fringe
- $56.78
BRCA0018-010 · Union rate · effective 2024-09-01
TERRAZZO WORKER/SETTER
- Base rate
- $49.62
- Fringe
- $15.26
- Base + fringe
- $64.88
BRCA0018-010 · Union rate · effective 2024-09-01
CARPENTER: (1) CARPENTER, CABINET INSTALLER, INSULATION INSTALLER, HARDWOOD FLOOR WORKER AND ACOUSTICAL INSTALLER
- Base rate
- $52.24
- Fringe
- $26.18
- Base + fringe
- $78.42
CARP0213-001 · Union rate · effective 2025-07-01
FOOTNOTE: WORK OF FORMING IN THE CONSTRUCTION OF OPEN CUT SEWERS OR STORM DRAINS, ON OPERATIONS IN WHICH HORIZONTAL LAGGING IS USED IN CONJUNCTION WITH STEEL H-BEAMS DRIVEN OR PLACED IN PRE- DRILLED HOLES, FOR THAT PORTION OF A LAGGED TRENCH AGAINST WHICH CONCRETE IS POURED, NAMELY, AS A SUBSTITUTE FOR BACK FORMS (WHICH WORK IS PERFORMED BY PILEDRIVERS): $0.13 PER HOUR ADDITIONAL
CARPENTER: (2) MILLWRIGHT
- Base rate
- $52.24
- Fringe
- $26.68
- Base + fringe
- $78.92
CARP0213-001 · Union rate · effective 2025-07-01
FOOTNOTE: WORK OF FORMING IN THE CONSTRUCTION OF OPEN CUT SEWERS OR STORM DRAINS, ON OPERATIONS IN WHICH HORIZONTAL LAGGING IS USED IN CONJUNCTION WITH STEEL H-BEAMS DRIVEN OR PLACED IN PRE- DRILLED HOLES, FOR THAT PORTION OF A LAGGED TRENCH AGAINST WHICH CONCRETE IS POURED, NAMELY, AS A SUBSTITUTE FOR BACK FORMS (WHICH WORK IS PERFORMED BY PILEDRIVERS): $0.13 PER HOUR ADDITIONAL
CARPENTER: (3) PILEDRIVERMEN/DERRICK BARGEMAN, BRIDGE OR DOCK CARPENTER, HEAVY FRAMER, ROCK BARGEMAN OR SCOWMAN, ROCKSLINGER, SHINGLER (COMMERCIAL)
- Base rate
- $52.37
- Fringe
- $26.18
- Base + fringe
- $78.55
CARP0213-001 · Union rate · effective 2025-07-01
FOOTNOTE: WORK OF FORMING IN THE CONSTRUCTION OF OPEN CUT SEWERS OR STORM DRAINS, ON OPERATIONS IN WHICH HORIZONTAL LAGGING IS USED IN CONJUNCTION WITH STEEL H-BEAMS DRIVEN OR PLACED IN PRE- DRILLED HOLES, FOR THAT PORTION OF A LAGGED TRENCH AGAINST WHICH CONCRETE IS POURED, NAMELY, AS A SUBSTITUTE FOR BACK FORMS (WHICH WORK IS PERFORMED BY PILEDRIVERS): $0.13 PER HOUR ADDITIONAL.
CARPENTER: (4) PNEUMATIC NAILER, POWER STAPLER
- Base rate
- $52.37
- Fringe
- $26.18
- Base + fringe
- $78.55
CARP0213-001 · Union rate · effective 2025-07-01
FOOTNOTE: WORK OF FORMING IN THE CONSTRUCTION OF OPEN CUT SEWERS OR STORM DRAINS, ON OPERATIONS IN WHICH HORIZONTAL LAGGING IS USED IN CONJUNCTION WITH STEEL H-BEAMS DRIVEN OR PLACED IN PRE- DRILLED HOLES, FOR THAT PORTION OF A LAGGED TRENCH AGAINST WHICH CONCRETE IS POURED, NAMELY, AS A SUBSTITUTE FOR BACK FORMS (WHICH WORK IS PERFORMED BY PILEDRIVERS): $0.13 PER HOUR ADDITIONAL
CARPENTER: (5) SAWFILER
- Base rate
- $52.34
- Fringe
- $26.18
- Base + fringe
- $78.52
CARP0213-001 · Union rate · effective 2025-07-01
FOOTNOTE: WORK OF FORMING IN THE CONSTRUCTION OF OPEN CUT SEWERS OR STORM DRAINS, ON OPERATIONS IN WHICH HORIZONTAL LAGGING IS USED IN CONJUNCTION WITH STEEL H-BEAMS DRIVEN OR PLACED IN PRE- DRILLED HOLES, FOR THAT PORTION OF A LAGGED TRENCH AGAINST WHICH CONCRETE IS POURED, NAMELY, AS A SUBSTITUTE FOR BACK FORMS (WHICH WORK IS PERFORMED BY PILEDRIVERS): $0.13 PER HOUR ADDITIONAL
CARPENTER: (6) SCAFFOLD BUILDER
- Base rate
- $45.37
- Fringe
- $25.43
- Base + fringe
- $70.80
CARP0213-001 · Union rate · effective 2025-07-01
FOOTNOTE: WORK OF FORMING IN THE CONSTRUCTION OF OPEN CUT SEWERS OR STORM DRAINS, ON OPERATIONS IN WHICH HORIZONTAL LAGGING IS USED IN CONJUNCTION WITH STEEL H-BEAMS DRIVEN OR PLACED IN PRE- DRILLED HOLES, FOR THAT PORTION OF A LAGGED TRENCH AGAINST WHICH CONCRETE IS POURED, NAMELY, AS A SUBSTITUTE FOR BACK FORMS (WHICH WORK IS PERFORMED BY PILEDRIVERS): $0.13 PER HOUR ADDITIONAL
CARPENTER: (7) TABLE POWER SAW OPERATOR
- Base rate
- $52.34
- Fringe
- $26.18
- Base + fringe
- $78.52
CARP0213-001 · Union rate · effective 2025-07-01
FOOTNOTE: WORK OF FORMING IN THE CONSTRUCTION OF OPEN CUT SEWERS OR STORM DRAINS, ON OPERATIONS IN WHICH HORIZONTAL LAGGING IS USED IN CONJUNCTION WITH STEEL H-BEAMS DRIVEN OR PLACED IN PRE- DRILLED HOLES, FOR THAT PORTION OF A LAGGED TRENCH AGAINST WHICH CONCRETE IS POURED, NAMELY, AS A SUBSTITUTE FOR BACK FORMS (WHICH WORK IS PERFORMED BY PILEDRIVERS): $0.13 PER HOUR ADDITIONAL
DIVER: (1) WET AMOUNTS IN "RATES' COLUMN ARE PER DAY
- Base rate
- $901.92
- Fringe
- $26.18
- Base + fringe
- $928.10
CARP0213-002 · Union rate · effective 2025-07-01
DIVER: (2) STANDBY AMOUNTS IN "RATES' COLUMN ARE PER DAY
- Base rate
- $450.96
- Fringe
- $26.18
- Base + fringe
- $477.14
CARP0213-002 · Union rate · effective 2025-07-01
DIVER: (3) TENDER AMOUNTS IN "RATES' COLUMN ARE PER DAY
- Base rate
- $442.96
- Fringe
- $26.18
- Base + fringe
- $469.14
CARP0213-002 · Union rate · effective 2025-07-01
DIVER: (4) ASSISTANT TENDER AMOUNTS IN "RATES' COLUMN ARE PER DAY
- Base rate
- $418.96
- Fringe
- $26.18
- Base + fringe
- $445.14
CARP0213-002 · Union rate · effective 2025-07-01
DRYWALL (DRYWALL INSTALLER/LATHER)
- Base rate
- $52.24
- Fringe
- $26.18
- Base + fringe
- $78.42
CARP0213-004 · Union rate · effective 2025-07-01
DRYWALL (STOCKER/SCRAPPER)
- Base rate
- $21.45
- Fringe
- $11.27
- Base + fringe
- $32.72
CARP0213-004 · Union rate · effective 2025-07-01
MODULAR FURNITURE INSTALLER
- Base rate
- $25.00
- Fringe
- $13.06
- Base + fringe
- $38.06
CARP0721-001 · Union rate · effective 2025-07-01
ELECTRICIAN: INSIDE ELECTRICAL WORK: JOURNEYMAN ELECTRICIAN FOOT NOTE: CABLE SPLICER & INSTRUMENT PERSON: RECIEVE 5% ADDITIONAL PER HOUR ABOVE JOURNEYMAN ELECTRICIAN BASIC HOURLY RATE. TUNNEL WORK: 10% ADDITIONAL PER HOUR
- Base rate
- $60.80
- Fringe
- $31.59
- Base + fringe
- $92.39
ELEC0011-004 · Union rate · effective 2023-06-30
ELECTRICIAN: INTELLIGENT TRANSPORTATION SYSTEMS STREET LIGHTING, TRAFFIC SIGNALS, CCTV ,AND UNDERGROUND SYSTEMS: JOURNEYMAN TRANSPORTATION ELECTRICIAN FOOT NOTE: CABLE SPLICER & INSTRUMENT PERSON: RECIEVE 5% ADDITIONAL PER HOUR ABOVE JOURNEYMAN ELECTRICIAN BASIC HOURLY RATE. TUNNEL WORK: 10% ADDITIONAL PER HOUR. SCOPE OF WORK - TRANSPORTATION SYSTEMS ELECTRICIAN: INSTALLATION OF STREET LIGHTS AND TRAFFIC SIGNALS,INCLUDING ELECTRICAL CIRCUITRY, PROGRAMMABLE CONTROLLERS, PEDESTAL-MOUNTED ELECTRICAL METER ENCLOSURES AND LAYING OF PRE-ASSEMBLED MULTI-CONDUCTOR CABLE IN DUCTS, LAYOUT OF ELECTRICAL SYSTEMS AND COMMUNICATION INSTALLATION, INCLUDING PROPER POSITION OF TRENCH DEPTHS AND RADIUS AT DUCT BANKS, LOCATION FOR MAN HOLES, PULL BOXES, STREET LIGHTS AND TRAFFIC SIGNALS. INSTALLATION OF UNDERGROUND DUCTS FOR ELECTRICAL,TELEPHONE, CABLE TELEVISION AND COMMUNICATION SYSTEMS. PULLING,TERMINATION AND SPLICING OF TRAFFIC SIGNAL AND STREET LIGHTING CONDUCTORS AND ELECTRICAL SYSTEMS INCLUDING INTERCONNECT,DETECTOR LOOP, FIBER OPTIC CABLE AND VIDEO/CABLE
- Base rate
- $60.80
- Fringe
- $31.59
- Base + fringe
- $92.39
ELEC0011-004 · Union rate · effective 2023-06-30
ELECTRICIAN: INTELLIGENT TRANSPORTATION SYSTEMS STREET LIGHTING, TRAFFIC SIGNALS, CCTV, AND UNDERGROUND SYSTEMS: TECHNICIAN FOOT NOTE: CABLE SPLICER & INSTRUMENT PERSON: RECIEVE 5% ADDITIONAL PER HOUR ABOVE JOURNEYMAN ELECTRICIAN BASIC HOURLY RATE. TUNNEL WORK: 10% ADDITIONAL PER HOUR. SCOPE OF WORK - TRANSPORTATION SYSTEMS TECHNICIAN: DISTRIBUTION OF MATERIAL AT JOB SITE, MANUAL EXCAVATION AND BACKFILL, INSTALLATION OF SYSTEM CONDUITS AND RACEWAYS FOR ELECTRICAL, TELEPHONE, CABLE TELEVISION AND COMMUNICATION SYSTEMS. PULLING, TERMINATING AND SPLICING OF TRAFFIC SIGNAL AND STREET LIGHTING CONDUCTORS AND ELECTRICAL SYSTEMS INCLUDING INTERCONNECT, DETECTOR LOOP, FIBER OPTIC CABLE AND VIDEO/DATA
- Base rate
- $45.60
- Fringe
- $31.14
- Base + fringe
- $76.74
ELEC0011-004 · Union rate · effective 2023-06-30
COMMUNICATIONS SYSTEM: INSTALLER COMMUNICATIONS & SYSTEMS WORK (EXCLUDES ANY WORK ON INTELLIGENT TRANSPORTATION SYSTEMS OR CCTV HIGHWAY SYSTEMS) SCOPE OF WORK THE WORK COVERED SHALL INCLUDE THE INSTALLATION, TESTING, SERVICE AND MAINTENANCE, OF THE FOLLOWING SYSTEMS THAT UTILIZE THE TRANSMISSION AND/OR TRANSFERENCE OF VOICE, SOUND, VISION AND DIGITAL FOR COMMERCIAL, EDUCATION, SECURITY AND ENTERTAINMENT PURPOSES FOR TV MONITORING AND SURVEILLANCE, BACKGROUND FOREGROUND MUSIC, INTERCOM AND TELEPHONE INTERCONNECT, INVENTORY CONTROL SYSTEMS, MICROWAVE TRANSMISSION, MULTI-MEDIA, MULTIPLEX, NURSE CALL SYSTEM, RADIO PAGE, SCHOOL INTERCOM AND SOUND, BURGLAR ALARMS AND LOW VOLTAGE MASTER CLOCK SYSTEMS. A. COMMUNICATION SYSTEMS THAT TRANSMIT OR RECEIVE INFORMATION AND/OR CONTROL SYSTEMS THAT ARE INTRINSIC TO THE ABOVE LISTED SYSTEMS SCADA (SUPERVISORY CONTROL/DATA ACQUISITION PCM (PULSE CODE MODULATION) INVENTORY CONTROL SYSTEMS DIGITAL DATA SYSTEMS BROADBAND & BASEBAND AND CARRIERS POINT OF SALE SYSTEMS VSAT DATA SYSTEMS DATA COMMUNICATION SYSTEMS RF AND REMOTE CONTROL SYSTEMS FIBER OPTIC DATA SYSTEMS B. SOUND AND VOICE TRANSMISSION/TRANSFERENCE SYSTEMS BACKGROUND-FOREGROUND MUSIC INTERCOM AND TELEPHONE INTERCONNECT SYSTEMS SOUND AND MUSICAL ENTERTAINMENT SYSTEMS NURSE CALL SYSTEMS RADIO PAGE SYSTEMS SCHOOL INTERCOM AND SOUND SYSTEMS BURGLAR ALARM SYSTEMS LOW-VOLTAGE MASTER CLOCK SYSTEMS MULTI-MEDIA/MULTIPLEX SYSTEMS TELEPHONE SYSTEMS RF SYSTEMS AND ANTENNAS AND WAVE GUIDE C. *FIRE ALARM SYSTEMS-INSTALLATION, WIRE PULLING AND TESTING. D. TELEVISION AND VIDEO SYSTEMS TELEVISION MONITORING AND SURVEILLANCE SYSTEMS VIDEO SECURITY SYSTEMS VIDEO ENTERTAINMENT SYSTEMS VIDEO EDUCATIONAL SYSTEMS CATV AND CCTV E. SECURITY SYSTEMS, PERIMETER SECURITY SYSTEMS, VIBRATION SENSOR SYSTEMS SONAR/INFRARED MONITORING EQUIPMENT, ACCESS CONTROL SYSTEMS, CARD ACCESS SYSTEMS *FIRE ALARM SYSTEMS 1. FIRE ALARMS-IN RACEWAYS: WIRE AND CABLE PULLING IN RACEWAYS PERFORMED BY ELECTRICIAN (INSIDE ELECTRICAL WORK) 2. FIRE ALARMS-OPEN WIRE SYSTEMS: INSTALLED BY THE COMMUNICATIONS SYSTEM INSTALLER
- Base rate
- $46.47
- Fringe
- $18.47
- Base + fringe
- $64.94
ELEC0011-007 · Union rate · effective 2024-01-01
LINE CONSTRUCTION: (1) LINEMAN; CABLE SPLICER HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND DAY AFTER THANKSGIVING, CHRISTMAS DAY
- Base rate
- $70.16
- Fringe
- $24.71
- Base + fringe
- $94.87
ELEC1245-001 · Union rate · effective 2025-01-01
LINE CONSTRUCTION: (2) EQUIPMENT SPECIALIST (OPERATES CRAWLER TRACTORS, COMMERCIAL MOTOR VEHICLES, BACKHOES, TRENCHERS, CRANES (50 TONS AND BELOW), OVERHEAD & UNDERGROUND DISTRIBUTION LINE EQUIPMENT) HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND DAY AFTER THANKSGIVING, CHRISTMAS DAY
- Base rate
- $53.30
- Fringe
- $22.26
- Base + fringe
- $75.56
ELEC1245-001 · Union rate · effective 2025-01-01
LINE CONSTRUCTION: (3) GROUNDMAN HOLIDAYS: NEW YEAR'S DAY, M.L. KING DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS DAY, THANKSGIVING DAY AND DAY AFTER THANKSGIVING, CHRISTMAS DAY
- Base rate
- $40.76
- Fringe
- $21.76
- Base + fringe
- $62.52
ELEC1245-001 · Union rate · effective 2025-01-01
ELEVATOR MECHANIC
- Base rate
- $69.43
- Fringe
- $38.44
- Base + fringe
- $107.87
ELEV0018-001 · Union rate · effective 2025-01-01
FOOTNOTE: A. PAID VACATION: EMPLOYER CONTRIBUTES 8% OF REGULAR HOURLY RATE AS VACATION PAY CREDIT FOR EMPLOYEES WITH MORE THAN 5 YEARS OF SERVICE, AND 6% FOR 6 MONTHS TO 5 YEARS OF SERVICE. B. PAID HOLIDAYS: NEW YEAR'S DAY, MEMORIAL DAY, INDEPENDENCE DAY, LABOR DAY, VETERANS' DAY, THANKSGIVING DAY, FRIDAY AFTER THANKSGIVING, AND CHRISTMAS DAY
OPERATOR, POWER EQUIPMENT: (1) LEVERMAN (DREDGING)
- Base rate
- $67.90
- Fringe
- $40.95
- Base + fringe
- $108.85
ENGI0012-004 · Union rate · effective 2025-08-01
OPERATOR, POWER EQUIPMENT: (2) DREDGE DOZER (DREDGING)
- Base rate
- $61.93
- Fringe
- $40.95
- Base + fringe
- $102.88
ENGI0012-004 · Union rate · effective 2025-08-01
OPERATOR, POWER EQUIPMENT: (3) DECKMATE (DREDGING)
- Base rate
- $61.82
- Fringe
- $40.95
- Base + fringe
- $102.77
ENGI0012-004 · Union rate · effective 2025-08-01
OPERATOR, POWER EQUIPMENT: (4) WINCH OPERATOR (STERN WINCH ON DREDGE) (DREDGING)
- Base rate
- $61.27
- Fringe
- $40.95
- Base + fringe
- $102.22
ENGI0012-004 · Union rate · effective 2025-08-01
OPERATOR, POWER EQUIPMENT: (5) FIREMAN-OILER, DECKHAND, BARGEMAN, LEVEEHAND (DREDGING)
- Base rate
- $60.73
- Fringe
- $40.95
- Base + fringe
- $101.68
ENGI0012-004 · Union rate · effective 2025-08-01
OPERATOR, POWER EQUIPMENT: (6) BARGE MATE (DREDGING)
- Base rate
- $61.34
- Fringe
- $40.95
- Base + fringe
- $102.29
ENGI0012-004 · Union rate · effective 2025-08-01
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 1- BARGEMAN; BRAKEMAN; COMPRESSOR OPERATOR; DITCH WITCH, WITH SEAT OR SIMILAR TYPE EQUIPMENT; ELEVATOR OPERATOR-INSIDE; ENGINEER OILER; FORKLIFT OPERATOR (INCLUDES LOED, LULL OR SIMILAR TYPES UNDER 5 TONS; GENERATOR OPERATOR; GENERATOR, PUMP OR COMPRESSOR PLANT OPERATOR; PUMP OPERATOR; SIGNALMAN; SWITCHMAN
- Base rate
- $63.40
- Fringe
- $33.20
- Base + fringe
- $96.60
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 2- ASPHALT-RUBBER PLANT OPERATOR (NURSE TANK OPERATOR);COIL TUBING RIG OPERATOR, CONCRETE MIXER OPERATOR-SKIP TYPE; CONVEYOR OPERATOR; FIREMAN; FORKLIFT OPERATOR (INCLUDES LOED, LULL OR SIMILAR TYPES OVER 5 TONS; HYDROSTATIC PUMP OPERATOR; OILER CRUSHER (ASPHALT OR CONCRETE PLANT); PETROMAT LAYDOWN MACHINE; PJU SIDE DUM JACK; SCREENING AND CONVEYOR MACHINE OPERATOR (OR SIMILAR TYPES); SKIPLOADER (WHEEL TYPE UP TO 3/4 YD. WITHOUT ATTACHMENT); TAR POT FIREMAN; TEMPORARY HEATING PLANT OPERATOR; TRENCHING MACHINE OILER
- Base rate
- $64.18
- Fringe
- $33.20
- Base + fringe
- $97.38
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 3- ASPHALT-RUBBER BLEND OPERATOR; BOBCAT OR SIMILAR TYPE (SKID STEER); EQUIPMENT GREASER (RACK); FORD FERGUSON (WITH DRAGTYPE ATTACHMENTS); HELICOPTER RADIOMAN (GROUND); STATIONARY PIPE WRAPPING AND CLEANING MACHINE OPERATOR
- Base rate
- $64.67
- Fringe
- $33.20
- Base + fringe
- $97.87
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 4- ASPHALT PLANT FIREMAN; BACKHOE OPERATOR (MINI-MAX OR SIMILAR TYPE); BORING MACHINE OPERATOR; BOXMAN OR MIXERMAN (ASPHALT OR CONCRETE); CHIP SPREADING MACHINE OPERATOR; CONCRETE CLEANING DECONTAMINATION MACHINE OPERATOR; CONCRETE PUMP OPERATOR (SMALL PORTABLE);DIRECT PUSH OPERATOR (GEOPROBE OR SIMILAR TYPES) DRILLING MACHINE OPERATOR, SMALL AUGER TYPES (TEXOMA SUPER ECONOMATIC OR SIMILAR TYPES - HUGHES 100 OR 200 OR SIMILAR TYPES - DRILLING DEPTH OF 30' MAXIMUM); EQUIPMENT GREASER (GREASE TRUCK); GUARD RAIL POST DRIVER OPERATOR; HIGHLINE CABLEWAY SIGNALMAN; HYDRA-HAMMER-AERO STOMPER; MICRO TUNNELING (ABOVE GROUND TUNNEL); POWER CONCRETE CURING MACHINE OPERATOR; POWER CONCRETE SAW OPERATOR; POWER-DRIVEN JUMBO FORM SETTER OPERATOR; POWER SWEEPER OPERATOR; ROCK WHEEL SAW/TRENCHER; ROLLER OPERATOR (COMPACTING); SCREED OPERATOR (ASPHALT OR CONCRETE); TRENCHING MACHINE OPERATOR (UP TO 6 FT.); VACUUM OR MUCH TRUCK
- Base rate
- $65.96
- Fringe
- $33.20
- Base + fringe
- $99.16
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 6- ARTICULATING MATERIAL HAULER; ASPHALT PLANT ENGINEER; BATCH PLANT OPERATOR; BIT SHARPENER; CONCRETE JOINT MACHINE OPERATOR (CANAL AND SIMILAR TYPE); CONCRETE PLANER OPERATOR; DANDY DIGGER; DECK ENGINE OPERATOR; DERRICKMAN (OILFIELD TYPE); DRILLING MACHINE OPERATOR, BUCKET OR AUGER TYPES (CALWELD 100 BUCKET OR SIMILAR TYPES - WATSON 1000 AUGER OR SIMILAR TYPES - TEXOMA 330, 500 OR 600 AUGER OR SIMILAR TYPES - DRILLING DEPTH OF 45' MAXIMUM); DRILLING MACHINE OPERATOR; HYDROGRAPHIC SEEDER MACHINE OPERATOR (STRAW, PULP OR SEED), JACKSON TRACK MAINTAINER, OR SIMILAR TYPE; KALAMAZOO SWITCH TAMPER, OR SIMILAR TYPE; MACHINE TOOL OPERATOR; MAGINNIS INTERNAL FULL SLAB VIBRATOR, MECHANICAL BERM, CURB OR GUTTER(CONCRETE OR ASPHALT); MECHANICAL FINISHER OPERATOR (CONCRETE, CLARY-JOHNSON-BIDWELL OR SIMILAR); MICRO TUNNEL SYSTEM (BELOW GROUND); PAVEMENT BREAKER OPERATOR (TRUCK MOUNTED); ROAD OIL MIXING MACHINE OPERATOR; ROLLER OPERATOR (ASPHALT OR FINISH), RUBBER-TIRED EARTH MOVING EQUIPMENT (SINGLE ENGINE, UP TO AND INCLUDING 25 YDS. STRUCK); SELF-PROPELLED TAR PIPELINING MACHINE OPERATOR; SKIPLOADER OPERATOR (CRAWLER AND WHEEL TYPE, OVER 3/4 YD. AND UP TO AND INCLUDING 1-1/2 YDS.); SLIP FORM PUMP OPERATOR (POWER DRIVEN HYDRAULIC LIFTING DEVICE FOR CONCRETE FORMS); TRACTOR OPERATOR-BULLDOZER, TAMPER-SCRAPER (SINGLE ENGINE, UP TO 100 H.P. FLYWHEEL AND SIMILAR TYPES, UP TO AND INCLUDING D-5 AND SIMILAR TYPES); TUGGER HOIST OPERATOR (1 DRUM); ULTRA HIGH PRESSURE WATERJET CUTTING TOOL SYSTEM OPERATOR; VACUUM BLASTING MACHINE OPERATOR
- Base rate
- $66.18
- Fringe
- $33.20
- Base + fringe
- $99.38
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 8- ASPHALT OR CONCRETE SPREADING OPERATOR (TAMPING OR FINISHING); ASPHALT PAVING MACHINE OPERATOR (BARBER GREENE OR SIMILAR TYPE); ASPHALT-RUBBER DISTRIBUTION OPERATOR; BACKHOE OPERATOR (UP TO AND INCLUDING 3/4 YD.), SMALL FORD, CASE OR SIMILAR TYPES; CABLE BUNDLING MACHINE OPERATOR (EXCLUDING HANDHELD); CABLE TRENCHING MACHINE OPERATOR (SPIDER PLOW OR SIMILAR TYPES) CAST-IN-PLACE PIPE LAYING MACHINE OPERATOR; COMBINATION MIXER AND COMPRESSOR OPERATOR (GUNITE WORK); COMPACTOR OPERATOR (SELF-PROPELLED); CONCRETE MIXER OPERATOR (PAVING); CRUSHING PLANT OPERATOR; DRILL DOCTOR; DRILLING MACHINE OPERATOR, BUCKET OR AUGER TYPES (CALWELD 150 BUCKET OR SIMILAR TYPES - WATSON 1500, 2000 2500 AUGER OR SIMILAR TYPES - TEXOMA 700, 800 AUGER OR SIMILAR TYPES - DRILLING DEPTH OF 60' MAXIMUM); ELEVATING GRADER OPERATOR; GRADE CHECKER; GRADALL OPERATOR; GROUTING MACHINE OPERATOR; HEAVY-DUTY REPAIRMAN; HEAVY EQUIPMENT ROBOTICS OPERATOR; KALAMAZOO BALLISTE REGULATOR OR SIMILAR TYPE; KOLMAN BELT LOADER AND SIMILAR TYPE; LE TOURNEAU BLOB COMPACTOR OR SIMILAR TYPE; LOADER OPERATOR (ATHEY, EUCLID, SIERRA AND SIMILAR TYPES); MOBARK CHIPPER OR SIMILAR; OZZIE PADDER OR SIMILAR TYPES; P.C. SLOT SAW; PNEUMATIC CONCRETE PLACING MACHINE OPERATOR (HACKLEY-PRESSWELL OR SIMILAR TYPE); PUMPCRETE GUN OPERATOR; RCM CEMENTING UNIT OPERATOR, RAIL/SWITCH GRINDER OPERATOR (HARSCO OR SIMILAR TYPES) ROCK DRILL OR SIMILAR TYPES; ROTARY DRILL OPERATOR (EXCLUDING CAISSON TYPE); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR (SINGLE ENGINE, CATERPILLAR, EUCLID, ATHEY WAGON AND SIMILAR TYPES WITH ANY AND ALL ATTACHMENTS OVER 25 YDS. UP TO AND INCLUDING 50 CU. YDS. STRUCK); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR (MULTIPLE ENGINE UP TO AND INCLUDING 25 YDS. STRUCK); RUBBER-TIRED SCRAPER OPERATOR (SELF-LOADING PADDLE WHEEL TYPE-JOHN DEERE, 1040 AND SIMILAR SINGLE UNIT); SELF- PROPELLED CURB AND GUTTER MACHINE OPERATOR; SHUTTLE BUGGY; SKIPLOADER OPERATOR (CRAWLER AND WHEEL TYPE OVER 1-1/2 YDS. UP TO AND INCLUDING 6-1/2 YDS.); SOIL REMEDIATION PLANT OPERATOR; SURFACE HEATERS AND PLANER OPERATOR; TRACTOR COMPRESSOR DRILL COMBINATION OPERATOR; TRACTOR OPERATOR (ANY TYPE LARGER THAN D-5 - 100 FLYWHEEL H.P. AND OVER, OR SIMILAR-BULLDOZER, TAMPER, SCRAPER AND PUSH TRACTOR SINGLE ENGINE); TRACTOR OPERATOR (BOOM ATTACHMENTS), TRAVELING PIPE WRAPPING, CLEANING AND BENDNG MACHINE OPERATOR; TRENCHING MACHINE OPERATOR (OVER 6 FT. DEPTH CAPACITY, MANUFACTURER'S RATING); TRENCHING MACHINE WITH ROAD MINER ATTACHMENT (OVER 6 FT DEPTH CAPACITY): ULTRA HIGH PRESSURE WATERJET CUTTING TOOL SYSTEM MECHANIC; WATER PULL (COMPACTION) OPERATOR
- Base rate
- $66.29
- Fringe
- $33.20
- Base + fringe
- $99.49
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 10- DRILLING MACHINE OPERATOR, BUCKET OR AUGER TYPES (CALWELD 200 B BUCKET OR SIMILAR TYPES-WATSON 3000 OR 5000 AUGER OR SIMILAR TYPES-TEXOMA 900 AUGER OR SIMILAR TYPES-DRILLING DEPTH OF 105' MAXIMUM); DUAL DRUM MIXER, DYNAMIC COMPACTOR LDC350 (OR SIMILAR TYPES); MONORAIL LOCOMOTIVE OPERATOR (DIESEL, GAS OR ELECTRIC); MOTOR PATROL-BLADE OPERATOR (SINGLE ENGINE); MULTIPLE ENGINE TRACTOR OPERATOR (EUCLID AND SIMILAR TYPE-EXCEPT QUAD 9 CAT.); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR (SINGLE ENGINE, OVER 50 YDS. STRUCK); PNEUMATIC PIPE RAMMING TOOL AND SIMILAR TYPES; PRESTRESSED WRAPPING MACHINE OPERATOR; RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR (SINGLE ENGINE, OVER 50 YDS. STRUCK); RUBBER TIRED EARTH MOVING EQUIPMENT OPERATOR (MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR OVER 25 YDS. AND UP TO 50 YDS. STRUCK), TOWER CRANE REPAIRMAN; TRACTOR LOADER OPERATOR (CRAWLER AND WHEEL TYPE OVER 6-1/2 YDS.); WOODS MIXER OPERATOR (AND SIMILAR PUGMILL EQUIPMENT)
- Base rate
- $66.41
- Fringe
- $33.20
- Base + fringe
- $99.61
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 12- AUTO GRADER OPERATOR; AUTOMATIC SLIP FORM OPERATOR; DRILLING MACHINE OPERATOR, BUCKET OR AUGER TYPES (CALWELD, AUGER 200 CA OR SIMILAR TYPES - WATSON, AUGER 6000 OR SIMILAR TYPES - HUGHES SUPER DUTY, AUGER 200 OR SIMILAR TYPES - DRILLING DEPTH OF 175' MAXIMUM); HOE RAM OR SIMILAR WITH COMPRESSOR; MASS EXCAVATOR OPERATOR LESS THA 750 CU. YARDS; MECHANICAL FINISHING MACHINE OPERATOR; MOBILE FORM TRAVELER OPERATOR; MOTOR PATROL OPERATOR (MULTI-ENGINE); PIPE MOBILE MACHINE OPERATOR; RUBBER-TIRED EARTH- MOVING EQUIPMENT OPERATOR (MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR TYPE, OVER 50 CU. YDS. STRUCK); RUBBER-TIRED SELF- LOADING SCRAPER OPERATOR (PADDLE-WHEEL-AUGER TYPE SELF-LOADING - TWO (2) OR MORE UNITS)
- Base rate
- $66.58
- Fringe
- $33.20
- Base + fringe
- $99.78
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 13- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM (SINGLE ENGINE, UP TO AND INCLUDING 25 YDS. STRUCK)
- Base rate
- $66.68
- Fringe
- $33.20
- Base + fringe
- $99.88
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 14- CANAL LINER OPERATOR; CANAL TRIMMER OPERATOR; REMOTE- CONTROL EARTH-MOVING EQUIPMENT OPERATOR (OPERATING A SECOND PIECE OF EQUIPMENT: $1.00 PER HOUR ADDITIONAL); WHEEL EXCAVATOR OPERATOR (OVER 750 CU. YDS.)
- Base rate
- $66.71
- Fringe
- $33.20
- Base + fringe
- $99.91
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 15- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM (SINGLE ENGINE, CATERPILLAR, EUCLID, ATHEY WAGON AND SIMILAR TYPES WITH ANY AND ALL ATTACHMENTS OVER 25 YDS. AND UP TO AND INCLUDING 50 YDS. STRUCK); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM (MULTIPLE ENGINE-UP TO AND INCLUDING 25 YDS. STRUCK)
- Base rate
- $66.79
- Fringe
- $33.20
- Base + fringe
- $99.99
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 16- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM (SINGLE ENGINE, OVER 50 YDS. STRUCK); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM (MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR, OVER 25 YDS. AND UP TO 50 YDS. STRUCK)
- Base rate
- $66.91
- Fringe
- $33.20
- Base + fringe
- $100.11
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 17- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH PUSH-PULL SYSTEM (MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR, OVER 50 CU. YDS. STRUCK); TANDEM TRACTOR OPERATOR (OPERATING CRAWLER TYPE TRACTORS IN TANDEM - QUAD 9 AND SIMILAR TYPE)
- Base rate
- $67.08
- Fringe
- $33.20
- Base + fringe
- $100.28
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 18- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM (SCRAPERS, BELLY DUMPS AND SIMILAR TYPES IN ANY COMBINATION, EXCLUDING COMPACTION UNITS - SINGLE ENGINE, UP TO AND INCLUDING 25 YDS. STRUCK)
- Base rate
- $67.18
- Fringe
- $33.20
- Base + fringe
- $100.38
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 19- ROTEX CONCRETE BELT OPERATOR (OR SIMILAR TYPES); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM (SCRAPERS, BELLY DUMPS AND SIMILAR TYPES IN ANY COMBINATION, EXCLUDING COMPACTION UNITS - SINGLE ENGINE, CATERPILLAR, EUCLID, ATHEY WAGON AND SIMILAR TYPES WITH ANY AND ALL ATTACHMENTS OVER 25 YDS.AND UP TO AND INCLUDING 50 CU. YDS. STRUCK); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM (SCRAPERS, BELLY DUMPS AND SIMILAR TYPES IN ANY COMBINATION, EXCLUDING COMPACTION UNITS - MULTIPLE ENGINE, UP TO AND INCLUDING 25 YDS. STRUCK)
- Base rate
- $67.29
- Fringe
- $33.20
- Base + fringe
- $100.49
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 2-0 RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM (SCRAPERS, BELLY DUMPS AND SIMILAR TYPES IN ANY COMBINATION, EXCLUDING COMPACTION UNITS - SINGLE ENGINE, OVER 50 YDS. STRUCK); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM (SCRAPERS, BELLY DUMPS, AND SIMILAR TYPES IN ANY COMBINATION, EXCLUDING COMPACTION UNITS - MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR, OVER 25 YDS. AND UP TO 50 YDS. STRUCK)
- Base rate
- $67.41
- Fringe
- $33.20
- Base + fringe
- $100.61
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 21- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING IN TANDEM (SCRAPERS, BELLY DUMPS AND SIMILAR TYPES IN ANY COMBINATION, EXCLUDING COMPACTION UNITS - MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR TYPE, OVER 50 CU. YDS. STRUCK)
- Base rate
- $67.58
- Fringe
- $33.20
- Base + fringe
- $100.78
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 22- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH THE TANDEM PUSH-PULL SYSTEM (SINGLE ENGINE, UP TO AND INCLUDING 25 YDS. STRUCK)
- Base rate
- $67.68
- Fringe
- $33.20
- Base + fringe
- $100.88
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 23- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH THE TANDEM PUSH-PULL SYSTEM (SINGLE ENGINE, CATERPILLAR, EUCLID, ATHEY WAGON AND SIMILAR TYPES WITH ANY AND ALL ATTACHMENTS OVER 25 YDS. AND UP TO AND INCLUDING 50 YDS. STRUCK); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING WITH THE TANDEM PUSH-PULL SYSTEM (MULTIPLE ENGINE, UP TO AND INCLUDING 25 YDS. STRUCK)
- Base rate
- $67.79
- Fringe
- $33.20
- Base + fringe
- $100.99
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 24- RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH THE TANDEM PUSH-PULL SYSTEM (SINGLE ENGINE, OVER 50 YDS. STRUCK); RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH THE TANDEM PUSH-PULL SYSTEM (MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR, OVER 25 YDS. AND UP TO 50 YDS. STRUCK)
- Base rate
- $67.91
- Fringe
- $33.20
- Base + fringe
- $101.11
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, ALL OTHER WORK: GROUP 25- CONCRETE PUMP OPERATOR-TRUCK MOUNTED; RUBBER-TIRED EARTH-MOVING EQUIPMENT OPERATOR, OPERATING EQUIPMENT WITH THE TANDEM PUSH-PULL SYSTEM (MULTIPLE ENGINE, EUCLID, CATERPILLAR AND SIMILAR TYPE, OVER 50 CU. YDS. STRUCK); SPYDER EXCAVATOR OPERATOR, WITH ALL ATTACHMENTS
- Base rate
- $68.08
- Fringe
- $33.20
- Base + fringe
- $101.28
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR.
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 1- Engineer oiler; Fork lift operator (includes loed, lull or similar types)
- Base rate
- $64.75
- Fringe
- $33.20
- Base + fringe
- $97.95
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR.
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 2- Truck crane oiler
- Base rate
- $65.53
- Fringe
- $33.20
- Base + fringe
- $98.73
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 3- A-frame or winch truck operator; Ross carrier operator (jobsite)
- Base rate
- $65.82
- Fringe
- $33.20
- Base + fringe
- $99.02
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 4- Bridge-type unloader and turntable operator; Helicopter hoist operator
- Base rate
- $65.96
- Fringe
- $33.20
- Base + fringe
- $99.16
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 5 HYDRAULIC BOOM TRUCK; STINGER CRANE (AUSTIN-WESTERN OR SIMILAR TYPE); TUGGER HOIST OPERATOR (1 DRUM)
- Base rate
- $66.18
- Fringe
- $33.20
- Base + fringe
- $99.38
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 6 Bridge crane operator; Cretor crane operator; Hoist operator (Chicago boom and similar type); Lift mobile operator; Lift slab machine operator (Vagtborg and similar types); Material hoist and/or manlift operator; Polar gantry crane operator; Self Climbing scaffold (or similar type); Shovel, backhoe, dragline, clamshell operator (over 3/4 yd. and up to 5 cu. yds. mrc); Tugger hoist operator
- Base rate
- $66.29
- Fringe
- $33.20
- Base + fringe
- $99.49
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 7 PEDESTAL CRANE OPERATOR; SHOVEL, BACKHOE, DRAGLINE, CLAMSHELL OPERATOR (OVER 5 CU. YDS. MRC); TOWER CRANE REPAIR; TUGGER HOIST OPERATOR (3 DRUM)
- Base rate
- $66.41
- Fringe
- $33.20
- Base + fringe
- $99.61
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 8 Crane operator (up to and including 25 ton capacity); Crawler transporter operator; Derrick barge operator (up to and including 25 ton capacity); Hoist operator, stiff legs, Guy derrick or similar type (up to and including 25 ton capacity); Shovel, backhoe, dragline, clamshell operator (over 7 cu. yds., M.R.C.)
- Base rate
- $66.58
- Fringe
- $33.20
- Base + fringe
- $99.78
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 9 Crane operator (over 25 tons and up to and including 50 tons mrc); Derrick barge operator (over 25 tons up to and including 50 tons mrc); Highline cableway operator; Hoist operator, stiff legs, Guy derrick or similar type (over 25 tons up to and including 50 tons mrc); K-crane operator; Polar crane operator; Self erecting tower crane operator maximum lifting capacity ten tons
- Base rate
- $66.75
- Fringe
- $33.20
- Base + fringe
- $99.95
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 10- Crane operator (over 50 tons and up to and including 100 tons mrc); Derrick barge operator (over 50 tons up to and including 100 tons mrc); Hoist operator, stiff legs, Guy derrick or similar type (over 50 tons up to and including 100 tons mrc), Mobile tower crane operator (over 50 tons, up to and including 100 tons M.R.C.)
- Base rate
- $67.75
- Fringe
- $33.20
- Base + fringe
- $100.95
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 11- Crane operator (over 100 tons and up to and including 200 tons mrc); Derrick barge operator (over 100 tons up to and including 200 tons mrc); Hoist operator, stiff legs, Guy derrick or similar type (over 100 tons up to and including 200 tons mrc); Mobile tower crane operator (over 100 tons up to and including 200 tons mrc) ; Tower crane operator and tower gantry
- Base rate
- $68.75
- Fringe
- $33.20
- Base + fringe
- $101.95
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 12- Crane operator (over 200 tons up to and including 300 tons mrc); Derrick barge operator (over 200 tons up to and including 300 tons mrc); Hoist operator, stiff legs, Guy derrick or similar type (over 200 tons, up to and including 300 tons mrc); Mobile tower crane operator (over 200 tons, up to and including 300 tons mrc)
- Base rate
- $69.75
- Fringe
- $33.20
- Base + fringe
- $102.95
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 PER HOUR SHALL BE PAID ON ALL POWER EQUIPMENT OPERATOR WORK ON THE FOLLOWNG MILITARY BASES: CHINA LAKE NAVAL RESERVE, VANDENBERG AFB, POINT ARGUELLO, SEELY NAVAL BASE, FORT IRWIN, NEBO ANNEX MARINE BASE, MARINE CORP LOGISTICS BASE YERMO, EDWARDS AFB, 29 PALMS MARINE BASE AND CAMP PENDLETON WORKERS REQUIRED TO SUIT UP AND WORK IN A HAZARDOUS MATERIAL ENVIRONMENT: $2.00 PER HOUR ADDITIONAL. COMBINATION MIXER AND COMPRESSOR OPERATOR ON GUNITE WORK SHALL BE CLASSIFIED AS A CONCRETE MOBILE MIXER OPERATOR
OPERATOR: POWER EQUIPMENT, CRANES, PILEDRIVING & HOISTING: GROUP 13 Crane operator (over 300 tons); Derrick barge operator (over 300 tons); Helicopter pilot; Hoist operator, stiff legs, Guy derrick or similar type (over 300 tons); Mobile tower crane operator (over 300 tons)
- Base rate
- $70.75
- Fringe
- $33.20
- Base + fringe
- $103.95
ENGI0012-024 · Union rate · effective 2025-07-01
OPERATOR: POWER EQUIPMENT, TUNNEL WORK: GROUP 1- Skiploader (wheel type up to 3/4 yd. without attachment)
- Base rate
- $65.25
- Fringe
- $33.20
- Base + fringe
- $98.45
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 per hour shall be paid on all Power Equipment Operator work on the followng Military Bases: China Lake Naval Reserve, Vandenberg AFB, Point Arguello, Seely Naval Base, Fort Irwin, Nebo Annex Marine Base, Marine Corp Logistics Base Yermo, Edwards AFB, 29 Palms Marine Base and Camp Pendleton Workers required to suit up and work in a hazardous material environment: $2.00 per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator
OPERATOR: POWER EQUIPMENT, TUNNEL WORK: GROUP 2- Power-driven jumbo form setter operator
- Base rate
- $66.03
- Fringe
- $33.20
- Base + fringe
- $99.23
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 per hour shall be paid on all Power Equipment Operator work on the followng Military Bases: China Lake Naval Reserve, Vandenberg AFB, Point Arguello, Seely Naval Base, Fort Irwin, Nebo Annex Marine Base, Marine Corp Logistics Base Yermo, Edwards AFB, 29 Palms Marine Base and Camp Pendleton Workers required to suit up and work in a hazardous material environment: $2.00 per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator
OPERATOR: POWER EQUIPMENT, TUNNEL WORK: GROUP 3- Dinkey locomotive or motorperson (up to and including 10 tons)
- Base rate
- $66.32
- Fringe
- $33.20
- Base + fringe
- $99.52
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 per hour shall be paid on all Power Equipment Operator work on the followng Military Bases: China Lake Naval Reserve, Vandenberg AFB, Point Arguello, Seely Naval Base, Fort Irwin, Nebo Annex Marine Base, Marine Corp Logistics Base Yermo, Edwards AFB, 29 Palms Marine Base and Camp Pendleton Workers required to suit up and work in a hazardous material environment: $2.00 per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator
OPERATOR: POWER EQUIPMENT, TUNNEL WORK: GROUP 4- Bit sharpener; Equipment greaser (grease truck); Slip form pump operator (power-driven hydraulic lifting device for concrete forms); Tugger hoist operator (1 drum); Tunnel locomotive operator (over 10 and up to and including 30 tons)
- Base rate
- $66.46
- Fringe
- $33.20
- Base + fringe
- $99.66
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 per hour shall be paid on all Power Equipment Operator work on the followng Military Bases: China Lake Naval Reserve, Vandenberg AFB, Point Arguello, Seely Naval Base, Fort Irwin, Nebo Annex Marine Base, Marine Corp Logistics Base Yermo, Edwards AFB, 29 Palms Marine Base and Camp Pendleton Workers required to suit up and work in a hazardous material environment: $2.00 per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator
OPERATOR: POWER EQUIPMENT, TUNNEL WORK: GROUP 5- Backhoe operator (up to and including 3/4 yd.); Small Ford, Case or similar; Drill doctor; Grouting machine operator; Heading shield operator; Heavy-duty repairperson; Loader operator (Athey, Euclid, Sierra and similar types); Mucking machine operator (1/4 yd., rubber-tired, rail or track type); Pneumatic concrete placing machine operator (Hackley-Presswell or similar type); Pneumatic heading shield (tunnel); Pumpcrete gun operator; Tractor compressor drill combination operator; Tugger hoist operator (2 drum); Tunnel locomotive operator (over 30 tons)
- Base rate
- $66.68
- Fringe
- $33.20
- Base + fringe
- $99.88
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 per hour shall be paid on all Power Equipment Operator work on the followng Military Bases: China Lake Naval Reserve, Vandenberg AFB, Point Arguello, Seely Naval Base, Fort Irwin, Nebo Annex Marine Base, Marine Corp Logistics Base Yermo, Edwards AFB, 29 Palms Marine Base and Camp Pendleton Workers required to suit up and work in a hazardous material environment: $2.00 per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator
OPERATOR: POWER EQUIPMENT, TUNNEL WORK: GROUP 6- Heavy Duty Repairman
- Base rate
- $66.79
- Fringe
- $33.20
- Base + fringe
- $99.99
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 per hour shall be paid on all Power Equipment Operator work on the followng Military Bases: China Lake Naval Reserve, Vandenberg AFB, Point Arguello, Seely Naval Base, Fort Irwin, Nebo Annex Marine Base, Marine Corp Logistics Base Yermo, Edwards AFB, 29 Palms Marine Base and Camp Pendleton Workers required to suit up and work in a hazardous material environment: $2.00 per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator
OPERATOR: POWER EQUIPMENT, TUNNEL WORK: GROUP 7- Tunnel mole boring machine operator
- Base rate
- $66.91
- Fringe
- $33.20
- Base + fringe
- $100.11
ENGI0012-024 · Union rate · effective 2025-07-01
PREMIUM PAY: $10.00 per hour shall be paid on all Power Equipment Operator work on the followng Military Bases: China Lake Naval Reserve, Vandenberg AFB, Point Arguello, Seely Naval Base, Fort Irwin, Nebo Annex Marine Base, Marine Corp Logistics Base Yermo, Edwards AFB, 29 Palms Marine Base and Camp Pendleton Workers required to suit up and work in a hazardous material environment: $2.00 per hour additional. Combination mixer and compressor operator on gunite work shall be classified as a concrete mobile mixer operator
IRONWORKER (FENCE ERECTOR)
- Base rate
- $45.78
- Fringe
- $26.51
- Base + fringe
- $72.29
IRON0433-006 · Union rate · effective 2025-01-01
IRONWORKER (ORNAMENTAL, REINFORCING AND STRUCTURAL)
- Base rate
- $50.70
- Fringe
- $35.15
- Base + fringe
- $85.85
IRON0433-006 · Union rate · effective 2025-01-01
BRICK TENDER
- Base rate
- $42.60
- Fringe
- $22.13
- Base + fringe
- $64.73
LABO0300-001 · Union rate · effective 2025-11-01
LABORER GROUP 1: CLEANING AND HANDLING OF PANEL FORMS; CONCRETE SCREEDING FOR ROUGH STRIKE-OFF; CONCRETE, WATER CURING; DEMOLITION LABORER, THE CLEANING OF BRICK IF PERFORMED BY A WORKER PERFORMING ANY OTHER PHASE OF DEMOLITION WORK, AND THE CLEANING OF LUMBER; FIRE WATCHER, LIMBER, BRUSH LOADER, PILER AND DEBRIS HANDLER; FLAG PERSON; GAS, OIL AND/OR WATER PIPELINE LABORER; LABORER, ASPHALT-RUBBER MATERIAL LOADER; LABORER, GENERAL OR CONSTRUCTION; LABORER, GENERAL CLEAN-UP; LABORER, LANDSCAPING; LABORER, JETTING; LABORER, TEMPORARY WATER AND AIR LINES; MATERIAL HOSE OPERATOR (WALLS, SLABS, FLOORS AND DECKS); PLUGGING, FILLING OF SHEE BOLT HOLES; DRY PACKING OF CONCRETE; RAILROAD MAINTENANCE, REPAIR TRACK PERSON AND ROAD BEDS; STREETCAR AND RAILROAD CONSTRUCTION TRACK LABORERS; RIGGING AND SIGNALING; SCALER; SLIP FORM RAISER; TAR AND MORTAR; TOOL CRIB OR TOOL HOUSE LABORER; TRAFFIC CONTROL BY ANY METHOD; WINDOW CLEANER; WIRE MESH PULLING - ALL CONCRETE POURING OPERATIONS
- Base rate
- $46.48
- Fringe
- $25.95
- Base + fringe
- $72.43
LABO0300-003 · Union rate · effective 2025-07-01
LABORER GROUP 2: ASPHALT SHOVELER; CEMENT DUMPER (ON 1 YD. OR LARGER MIXER AND HANDLING BULK CEMENT); CESSPOOL DIGGER AND INSTALLER; CHUCKTENDER; CHUTE HANDLER, POURING CONCRETE, THE HANDLING OF THE CHUTE FROM READYMIX TRUCKS, SUCH AS WALLS, SLABS, DECKS, FLOORS, FOUNDATION, FOOTINGS, CURBS, GUTTERS AND SIDEWALKS; CONCRETE CURER, IMPERVIOUS MEMBRANE AND FORM OILER; CUTTING TORCH OPERATOR (DEMOLITION); FINE GRADER, HIGHWAYS AND STREET PAVING, AIRPORT, RUNWAYS AND SIMILAR TYPE HEAVY CONSTRUCTION; GAS, OIL AND/OR WATER PIPELINE WRAPPER - POT TENDER AND FORM PERSON; GUINEA CHASER; HEADERBOARD PERSON - ASPHALT; LABORER, PACKING ROD STEEL AND PANS; MEMBRANE VAPOR BARRIER INSTALLER; POWER BROOM SWEEPER (SMALL); RIPRAP STONEPAVER, PLACING STONE OR WET SACKED CONCRETE; ROTO SCRAPER AND TILLER; SANDBLASTER (POT TENDER); SEPTIC TANK DIGGER AND INSTALLER(LEAD); TANK SCALER AND CLEANER; TREE CLIMBER, FALLER, CHAIN SAW OPERATOR, PITTSBURGH CHIPPER AND SIMILAR TYPE BRUSH SHREDDER; UNDERGROUND LABORER, INCLUDING CAISSON BELLOWER
- Base rate
- $47.03
- Fringe
- $25.95
- Base + fringe
- $72.98
LABO0300-003 · Union rate · effective 2025-07-01
LABORER GROUP 3: BUGGYMOBILE PERSON; CONCRETE CUTTING TORCH; CONCRETE PILE CUTTER; DRILLER, JACKHAMMER, 2-1/2 FT. DRILL STEEL OR LONGER; DRI-PAK-IT MACHINE; GAS, OIL AND/OR WATER PIPELINE WRAPPER, 6-IN. PIPE AND OVER, BY ANY METHOD, INSIDE AND OUT; HIGH SCALER (INCLUDING DRILLING OF SAME); HYDRO SEEDER AND SIMILAR TYPE; IMPACT WRENCH MULTI-PLATE; KETTLE PERSON, POT PERSON AND WORKERS APPLYING ASPHALT, LAY-KOLD, CREOSOTE, LIME CAUSTIC AND SIMILAR TYPE MATERIALS ("APPLYING" MEANS APPLYING, DIPPING, BRUSHING OR HANDLING OF SUCH MATERIALS FOR PIPE WRAPPING AND WATERPROOFING); OPERATOR OF PNEUMATIC, GAS, ELECTRIC TOOLS, VIBRATING MACHINE, PAVEMENT BREAKER, AIR BLASTING, COME-ALONGS, AND SIMILAR MECHANICAL TOOLS NOT SEPARATELY CLASSIFIED HEREIN; PIPELAYER'S BACKUP PERSON, COATING, GROUTING, MAKING OF JOINTS, SEALING, CAULKING, DIAPERING AND INCLUDING RUBBER GASKET JOINTS, POINTING AND ANY AND ALL OTHER SERVICES; ROCK SLINGER; ROTARY SCARIFIER OR MULTIPLE HEAD CONCRETE CHIPPING SCARIFIER; STEEL HEADERBOARD AND GUIDELINE SETTER; TAMPER, BARKO, WACKER AND SIMILAR TYPE; TRENCHING MACHINE, HAND-PROPELLED
- Base rate
- $47.58
- Fringe
- $25.95
- Base + fringe
- $73.53
LABO0300-003 · Union rate · effective 2025-07-01
LABORER GROUP 4: ASPHALT RAKER, LUTE PERSON, IRONER, ASPHALT DUMP PERSON, AND ASPHALT SPREADER BOXES (ALL TYPES); CONCRETE CORE CUTTER (WALLS, FLOORS OR CEILINGS), GRINDER OR SANDER; CONCRETE SAW PERSON, CUTTING WALLS OR FLAT WORK, SCORING OLD OR NEW CONCRETE; CRIBBER, SHORER, LAGGING, SHEETING AND TRENCH BRACING, HAND-GUIDED LAGGING HAMMER; HEAD ROCK SLINGER; LABORER, ASPHALT- RUBBER DISTRIBUTOR BOOT PERSON; LASER BEAM IN CONNECTION WITH LABORERS' WORK; OVERSIZE CONCRETE VIBRATOR OPERATOR, 70 LBS. AND OVER; PIPELAYER PERFORMING ALL SERVICES IN THE LAYING AND INSTALLATION OF PIPE FROM THE POINT OF RECEIVING PIPE IN THE DITCH UNTIL COMPLETION OF OPERATION, INCLUDING ANY AND ALL FORMS OF TUBULAR MATERIAL, WHETHER PIPE, METALLIC OR NON-METALLIC, CONDUIT AND ANY OTHER STATIONARY TYPE OF TUBULAR DEVICE USED FOR THE CONVEYING OF ANY SUBSTANCE OR ELEMENT, WHETHER WATER, SEWAGE, SOLID GAS, AIR, OR OTHER PRODUCT WHATSOEVER AND WITHOUT REGARD TO THE NATURE OF MATERIAL FROM WHICH THE TUBULAR MATERIAL IS FABRICATED; NO-JOINT PIPE AND STRIPPING OF SAME; PREFABRICATED MANHOLE INSTALLER; SANDBLASTER (NOZZLE PERSON), WATER BLASTING, PORTA SHOT-BLAST
- Base rate
- $49.13
- Fringe
- $25.95
- Base + fringe
- $75.08
LABO0300-003 · Union rate · effective 2025-07-01
LABORER GROUP 5: BLASTER POWDER, ALL WORK OF LOADING HOLES, PLACING AND BLASTING OF ALL POWDER AND EXPLOSIVES OF WHATEVER TYPE, REGARDLESS OF METHOD USED FOR SUCH LOADING AND PLACING; DRILLER: ALL POWER DRILLS, EXCLUDING JACKHAMMER, WHETHER CORE, DIAMOND, WAGON, TRACK, MULTIPLE UNIT, AND ANY AND ALL OTHER TYPES OF MECHANICAL DRILLS WITHOUT REGARD TO THE FORM OF MOTIVE POWER; TOXIC WASTE REMOVAL
- Base rate
- $49.48
- Fringe
- $25.95
- Base + fringe
- $75.43
LABO0300-003 · Union rate · effective 2025-07-01
LABORER, TUNNEL: GROUP 1: BATCH PLANT LABORER; CHANGEHOUSE PERSON; DUMP PERSON; DUMP PERSON (OUTSIDE); SWAMPER (BRAKE PERSON AND SWITCH PERSON ON TUNNEL WORK); TUNNEL MATERIALS HANDLING PERSON; NIPPER; POT TENDER, USING MASTIC OR OTHER MATERIALS (FOR EXAMPLE, BUT NOT BY WAY OF LIMITATION, SHOTCRETE, ETC.)
- Base rate
- $53.60
- Fringe
- $25.74
- Base + fringe
- $79.34
LABO0300-003 · Union rate · effective 2025-07-01
LABORER, TUNNEL: GROUP 2: CHUCKTENDER, CABLETENDER; LOADING AND UNLOADING AGITATOR CARS;; VIBRATOR PERSON, JACK HAMMER, PNEUMATIC TOOLS (EXCEPT DRILLER); BULL GANG MUCKER, TRACK PERSON; CONCRETE CREW, INCLUDING RODDER AND SPREADER
- Base rate
- $53.92
- Fringe
- $25.74
- Base + fringe
- $79.66
LABO0300-003 · Union rate · effective 2025-07-01
LABORER, TUNNEL: GROUP 3: BLASTER, DRILLER, POWDER PERSON; CHEMICAL GROUT JET PERSON; CHERRY PICKER PERSON; GROUT GUN PERSON; GROUT MIXER PERSON; GROUT PUMP PERSON; JACKLEG MINER; JUMBO PERSON; KEMPER AND OTHER PNEUMATIC CONCRETE PLACER OPERATOR; MINER, TUNNEL (HAND OR MACHINE); NOZZLE PERSON; OPERATING OF TROWELING AND/OR GROUTING MACHINES; POWDER PERSON (PRIMER HOUSE); PRIMER PERSON; SANDBLASTER; SHOTCRETE PERSON; STEEL FORM RAISER AND SETTER; TIMBER PERSON, RETIMBER PERSON, WOOD OR STEEL; TUNNEL CONCRETE FINISHER
- Base rate
- $54.38
- Fringe
- $25.74
- Base + fringe
- $80.12
LABO0300-003 · Union rate · effective 2025-07-01
LABORER, TUNNEL: GROUP 4: DIAMOND DRILLER; SANDBLASTER; SHAFT AND RAISE WORK
- Base rate
- $55.07
- Fringe
- $25.74
- Base + fringe
- $80.81
LABO0300-003 · Union rate · effective 2025-07-01
ASBESTOS REMOVAL LABORER SCOPE OF WORK: INCLUDES SITE MOBILIZATION, INITIAL SITE CLEANUP, SITE PREPARATION, REMOVAL OF ASBESTOS-CONTAINING MATERIAL AND TOXIC WASTE, ENCAPSULATION, ENCLOSURE AND DISPOSAL OF ASBESTOS- CONTAINING MATERIALS AND TOXIC WASTE BY HAND OR WITH EQUIPMENT OR MACHINERY; SCAFFOLDING, FABRICATION OF TEMPORARY WOODEN BARRIERS AND ASSEMBLY OF DECONTAMINATION STATIONS
- Base rate
- $46.48
- Fringe
- $25.93
- Base + fringe
- $72.41
LABO0300-005 · Union rate · effective 2025-07-01
LABORER, GUNITE: GROUP 1 RODMEN, NOZZLEMEN
- Base rate
- $55.88
- Fringe
- $23.77
- Base + fringe
- $79.65
LABO0345-001 · Union rate · effective 2025-07-01
FOOTNOTE: GUNITE PREMIUM PAY: WORKERS WORKING FROM A BOSN'N'S CHAIR OR SUSPENDED FROM A ROPE OR CABLE SHALL RECEIVE 40 CENTS PER HOUR ABOVE THE FOREGOING APPLICABLE CLASSIFICATION RATES. WORKERS DOING GUNITE AND/OR SHOTCRETE WORK IN A TUNNEL SHALL RECEIVE 35 CENTS PER HOUR ABOVE THE FOREGOING APPLICABLE CLASSIFICATION RATES, PAID ON A PORTAL-TO-PORTAL BASIS. ANY WORK PERFORMED ON, IN OR ABOVE ANY SMOKE STACK, SILO, STORAGE ELEVATOR OR SIMILAR TYPE OF STRUCTURE, WHEN SUCH STRUCTURE IS IN EXCESS OF 75'-0" ABOVE BASE LEVEL AND WHICH WORK MUST BE PERFORMED IN WHOLE OR IN PART MORE THAN 75'-0" ABOVE BASE LEVEL, THAT WORK PERFORMED ABOVE THE 75'-0" LEVEL SHALL BE COMPENSATED FOR AT 35 CENTS PER HOUR ABOVE THE APPLICABLE CLASSIFICATION WAGE RATE
LABORER, GUNITE: GROUP 2 GUNMEN
- Base rate
- $54.93
- Fringe
- $23.77
- Base + fringe
- $78.70
LABO0345-001 · Union rate · effective 2025-07-01
FOOTNOTE: GUNITE PREMIUM PAY: WORKERS WORKING FROM A BOSN'N'S CHAIR OR SUSPENDED FROM A ROPE OR CABLE SHALL RECEIVE 40 CENTS PER HOUR ABOVE THE FOREGOING APPLICABLE CLASSIFICATION RATES. WORKERS DOING GUNITE AND/OR SHOTCRETE WORK IN A TUNNEL SHALL RECEIVE 35 CENTS PER HOUR ABOVE THE FOREGOING APPLICABLE CLASSIFICATION RATES, PAID ON A PORTAL-TO-PORTAL BASIS. ANY WORK PERFORMED ON, IN OR ABOVE ANY SMOKE STACK, SILO, STORAGE ELEVATOR OR SIMILAR TYPE OF STRUCTURE, WHEN SUCH STRUCTURE IS IN EXCESS OF 75'-0" ABOVE BASE LEVEL AND WHICH WORK MUST BE PERFORMED IN WHOLE OR IN PART MORE THAN 75'-0" ABOVE BASE LEVEL, THAT WORK PERFORMED ABOVE THE 75'-0" LEVEL SHALL BE COMPENSATED FOR AT 35 CENTS PER HOUR ABOVE THE APPLICABLE CLASSIFICATION WAGE RATE
LABORER, GUNITE: GROUP 3 REBOUNDMEN
- Base rate
- $51.39
- Fringe
- $23.77
- Base + fringe
- $75.16
LABO0345-001 · Union rate · effective 2025-07-01
FOOTNOTE: GUNITE PREMIUM PAY: WORKERS WORKING FROM A BOSN'N'S CHAIR OR SUSPENDED FROM A ROPE OR CABLE SHALL RECEIVE 40 CENTS PER HOUR ABOVE THE FOREGOING APPLICABLE CLASSIFICATION RATES. WORKERS DOING GUNITE AND/OR SHOTCRETE WORK IN A TUNNEL SHALL RECEIVE 35 CENTS PER HOUR ABOVE THE FOREGOING APPLICABLE CLASSIFICATION RATES, PAID ON A PORTAL-TO-PORTAL BASIS. ANY WORK PERFORMED ON, IN OR ABOVE ANY SMOKE STACK, SILO, STORAGE ELEVATOR OR SIMILAR TYPE OF STRUCTURE, WHEN SUCH STRUCTURE IS IN EXCESS OF 75'-0" ABOVE BASE LEVEL AND WHICH WORK MUST BE PERFORMED IN WHOLE OR IN PART MORE THAN 75'-0" ABOVE BASE LEVEL, THAT WORK PERFORMED ABOVE THE 75'-0" LEVEL SHALL BE COMPENSATED FOR AT 35 CENTS PER HOUR ABOVE THE APPLICABLE CLASSIFICATION WAGE RATE
LABORERS: HORIZONTAL DIRECTIONAL DRILLING: (1) DRILLING CREW LABORER
- Base rate
- $47.94
- Fringe
- $20.86
- Base + fringe
- $68.80
LABO1184-001 · Union rate · effective 2025-07-01
LABORERS: HORIZONTAL DIRECTIONAL DRILLING: (2) VEHICLE OPERATOR/HAULER
- Base rate
- $48.11
- Fringe
- $20.86
- Base + fringe
- $68.97
LABO1184-001 · Union rate · effective 2025-07-01
LABORERS: HORIZONTAL DIRECTIONAL DRILLING: (3) HORIZONTAL DIRECTIONAL DRILL OPERATOR
- Base rate
- $49.96
- Fringe
- $20.86
- Base + fringe
- $70.82
LABO1184-001 · Union rate · effective 2025-07-01
LABORERS: HORIZONTAL DIRECTIONAL DRILLING: (4) ELECTRONIC TRACKING LOCATOR
- Base rate
- $51.96
- Fringe
- $20.86
- Base + fringe
- $72.82
LABO1184-001 · Union rate · effective 2025-07-01
LABORERS: , STRIPING/SLURRY SEAL: GROUP 1 PROTECTIVE COATING, PAVEMENT SEALING, INCLUDING REPAIR AND FILLING OF CRACKS BY ANY METHOD ON ANY SURFACE IN PARKING LOTS, GAME COURTS AND PLAYGROUNDS; CARSTOPS; OPERATION OF ALL RELATED MACHINERY AND EQUIPMENT; EQUIPMENT REPAIR TECHNICIAN
- Base rate
- $49.30
- Fringe
- $23.97
- Base + fringe
- $73.27
LABO1184-001 · Union rate · effective 2025-07-01
LABORERS: , STRIPING/SLURRY SEAL: GROUP 2 TRAFFIC SURFACE ABRASIVE BLASTER; POT TENDER - REMOVAL OF ALL TRAFFIC LINES AND MARKINGS BY ANY METHOD (SANDBLASTING, WATERBLASTING, GRINDING, ETC.) AND PREPARATION OF SURFACE FOR COATINGS. TRAFFIC CONTROL PERSON: CONTROLLING AND DIRECTING TRAFFIC THROUGH BOTH CONVENTIONAL AND MOVING LANE CLOSURES; OPERATION OF ALL RELATED MACHINERY AND EQUIPMENT
- Base rate
- $50.60
- Fringe
- $23.97
- Base + fringe
- $74.57
LABO1184-001 · Union rate · effective 2025-07-01
LABORERS: , STRIPING/SLURRY SEAL: GROUP 3 TRAFFIC DELINEATING DEVICE APPLICATOR: LAYOUT AND APPLICATION OF PAVEMENT MARKERS, DELINEATING SIGNS, RUMBLE AND TRAFFIC BARS, ADHESIVES, GUIDE MARKERS, OTHER TRAFFIC DELINEATING DEVICES INCLUDING TRAFFIC CONTROL. THIS CATEGORY INCLUDES ALL TRAFFIC RELATED SURFACE PREPARATION (SANDBLASTING, WATERBLASTING, GRINDING) AS PART OF THE APPLICATION PROCESS. TRAFFIC PROTECTIVE DELINEATING SYSTEM INSTALLER: REMOVES, RELOCATES, INSTALLS, PERMANENTLY AFFIXED ROADSIDE AND PARKING DELINEATION BARRICADES, FENCING, CABLE ANCHOR, GUARD RAIL, REFERENCE SIGNS, MONUMENT MARKERS; OPERATION OF ALL RELATED MACHINERY AND EQUIPMENT; POWER BROOM SWEEPER
- Base rate
- $52.61
- Fringe
- $23.97
- Base + fringe
- $76.58
LABO1184-001 · Union rate · effective 2025-07-01
LABORERS: , STRIPING/SLURRY SEAL: GROUP 4 STRIPER: LAYOUT AND APPLICATION OF TRAFFIC STRIPES AND MARKINGS; HOT THERMO PLASTIC; TAPE TRAFFIC STRIPES AND MARKINGS, INCLUDING TRAFFIC CONTROL; OPERATION OF ALL RELATED MACHINERY AND EQUIPMENT
- Base rate
- $54.35
- Fringe
- $23.97
- Base + fringe
- $78.32
LABO1184-001 · Union rate · effective 2025-07-01
LABORER: PLASTER CLEAN-UP LABORER WORK ON A SWING STAGE SCAFFOLD: $1.00 PER HOUR ADDITIONAL
- Base rate
- $46.17
- Fringe
- $25.97
- Base + fringe
- $72.14
LABO1414-001 · Union rate · effective 2025-08-06
LABORER: PLASTER TENDER WORK ON A SWING STAGE SCAFFOLD: $1.00 PER HOUR ADDITIONAL
- Base rate
- $48.72
- Fringe
- $25.97
- Base + fringe
- $74.69
LABO1414-001 · Union rate · effective 2025-08-06
PAINTERS: INCLUDING LEAD ABATEMENT: (2) ALL OTHER WORK
- Base rate
- $38.52
- Fringe
- $18.64
- Base + fringe
- $57.16
PAIN0036-001 · Union rate · effective 2023-07-01
DRYWALL FINISHER/TAPER (ANTELOPE VALLEY NORTH OF THE FOLLOWING BOUNDARY: KERN COUNTY LINE TO HWY. #5, SOUTH ON HWY. #5 TO HWY. N2, EAST ON N2 TO PALMDALE BLVD., TO HWY. #14, SOUTH TO HWY. #18, EAST TO HWY. #395)
- Base rate
- $45.20
- Fringe
- $26.82
- Base + fringe
- $72.02
PAIN0036-006 · Union rate · effective 2024-09-01
DRYWALL FINISHER/TAPER (REMAINDER OF LOS ANGELES COUNTY)
- Base rate
- $49.33
- Fringe
- $26.82
- Base + fringe
- $76.15
PAIN0036-006 · Union rate · effective 2024-09-01
GLAZIER
- Base rate
- $53.05
- Fringe
- $30.64
- Base + fringe
- $83.69
PAIN0036-015 · Union rate · effective 2025-01-01
FOOTNOTE: ADDITIONAL $1.25 PER HOUR FOR WORK IN A CONDOR, FROM THE THIRD (3RD) FLOOR AND UP ADDITIONAL $1.25 PER HOUR FOR WORK ON THE OUTSIDE OF THE BUILDING FROM A SWING STAGE OR ANY SUSPENDED CONTRIVANCE, FROM THE GROUND UP
SOFT FLOOR LAYER
- Base rate
- $45.15
- Fringe
- $19.43
- Base + fringe
- $64.58
PAIN1247-002 · Union rate · effective 2025-01-01
PLASTERER
- Base rate
- $47.37
- Fringe
- $19.64
- Base + fringe
- $67.01
PLAS0200-009 · Union rate · effective 2022-08-03
CEMENT MASON/CONCRETE FINISHER
- Base rate
- $47.70
- Fringe
- $27.07
- Base + fringe
- $74.77
PLAS0500-002 · Union rate · effective 2025-07-01
PLUMBER/PIPEFITTER (WORK ONLY ON NEW ADDITIONS AND REMODELING OF BARS, RESTAURANT, STORES AND COMMERCIAL BUILDINGS NOT TO EXCEED 5,000 SQ. FT. OF FLOOR SPACE)
- Base rate
- $59.85
- Fringe
- $25.83
- Base + fringe
- $85.68
PLUM0016-001 · Union rate · effective 2025-09-01
PLUMBER/PIPEFITTER (ALL OTHER WORK EXCEPT WORK ON NEW ADDITIONS AND REMODELING OF BARS, RESTAURANT, STORES AND COMMERCIAL BUILDINGS NOT TO EXCEED 5,000 SQ. FT. OF FLOOR SPACE AND WORK ON STRIP MALLS, LIGHT COMMERCIAL, TENANT IMPROVEMENT AND REMODEL WORK)
- Base rate
- $61.73
- Fringe
- $26.81
- Base + fringe
- $88.54
PLUM0016-001 · Union rate · effective 2025-09-01
PLUMBER/PIPEFITTER (WORK ONLY ON STRIP MALLS, LIGHT COMMERCIAL, TENANT IMPROVEMENT AND REMODEL WORK)
- Base rate
- $44.29
- Fringe
- $24.16
- Base + fringe
- $68.45
PLUM0016-001 · Union rate · effective 2025-09-01
PLUMBER (LANDSCAPE/IRRIGATION FITTER)
- Base rate
- $44.75
- Fringe
- $26.20
- Base + fringe
- $70.95
PLUM0345-001 · Union rate · effective 2025-09-01
PLUMBER (SEWER & STORM DRAIN WORK)
- Base rate
- $48.84
- Fringe
- $23.58
- Base + fringe
- $72.42
PLUM0345-001 · Union rate · effective 2025-09-01
ROOFER
- Base rate
- $52.63
- Fringe
- $20.73
- Base + fringe
- $73.36
ROOF0036-002 · Union rate · effective 2025-08-01
FOOTNOTE: PITCH PREMIUM: WORK ON WHICH EMPLOYEES ARE EXPOSED TO PITCH FUMES OR REQUIRED TO HANDLE PITCH, PITCH BASE OR PITCH IMPREGNATED PRODUCTS, OR ANY MATERIAL CONTAINING COAL TAR PITCH, THE ENTIRE ROOFING CREW SHALL RECEIVE $1.75 PER HOUR "PITCH PREMIUM" PAY
SPRINKLER FITTER (DOES NOT INCLUDE THE CITY OF POMONA, CATALINA ISLAND, AND THAT PART OF LOS ANGELES COUNTY WITHIN 25 MILES OF THE CITY LIMITS OF LOS ANGELES)
- Base rate
- $50.79
- Fringe
- $29.80
- Base + fringe
- $80.59
SFCA0669-013 · Union rate · effective 2026-01-01
SPRINKLER FITTER: FIRE (THE CITY OF POMOMA, CATALINA ISLAND, AND THAT PART OF LOS ANGELES COUNTY WITHIN 25 MILES OF THE CITY LIMITS OF LOS ANGELES)
- Base rate
- $58.60
- Fringe
- $33.65
- Base + fringe
- $92.25
SFCA0709-005 · Union rate · effective 2025-09-01
SHEET METAL WORKER: (1) LIGHT COMMERCIAL: WORK ON GENERAL SHEET METAL AND HEATING AND AC UP TO 4000 SQ FT. (LOS ANGELES (SOUTH OF A STRAIGHT LINE BETWEEN GORMAN AND BIG PINES INCLUDING CATALINA ISLAND))
- Base rate
- $35.57
- Fringe
- $10.63
- Base + fringe
- $46.20
SHEE0105-002 · Union rate · effective 2025-01-01
SHEET METAL WORKER: (1) COMMERCIAL - NEW CONSTRUCTION AND REMODEL WORK (LOS ANGELES (SOUTH OF A STRAIGHT LINE DRAWN BETWEEN GORMAN AND BIG PINES)AND CATALINA ISLAND, INYO, KERN (NORTHEAST PART, EAST OF HWY 395), MONO ORANGE, RIVERSIDE, AND SAN BERNARDINO COUNTIES)
- Base rate
- $59.31
- Fringe
- $30.43
- Base + fringe
- $89.74
SHEE0105-003 · Union rate · effective 2025-01-01
SHEET METAL WORKER (KERN (EXCLUDING PORTION EAST OF HWY 395) & LOS ANGELES (NORTH OF A STRAIGHT LINE DRAWN BETWEEN GORMAN AND BIG PINES INCLUDING CITIES OF LANCASTER AND PALMDALE) COUNTIES)
- Base rate
- $45.98
- Fringe
- $29.24
- Base + fringe
- $75.22
SHEE0105-004 · Union rate · effective 2023-07-01
TRUCK DRIVER GROUP 1 TRUCK DRIVER WORK ON ALL MILITARY BASES:
- Base rate
- $41.59
- Fringe
- $35.69
- Base + fringe
- $77.28
TEAM0011-002 · Union rate · effective 2025-07-01
PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB]
TRUCK DRIVER GROUP 2 DRIVER OF VEHICLE OR COMBINATION OF VEHICLES - 2 AXLES; TRAFFIC CONTROL PILOT CAR EXCLUDING MOVING HEAVY EQUIPMENT PERMIT LOAD; TRUCK MOUNTED BROOM WORK ON ALL MILITARY BASES:
- Base rate
- $41.74
- Fringe
- $35.69
- Base + fringe
- $77.43
TEAM0011-002 · Union rate · effective 2025-07-01
PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB]
TRUCK DRIVER GROUP 3 DRIVER OF VEHICLE OR COMBINATION OF VEHICLES - 3 AXLES; BOOT PERSON; CEMENT MASON DISTRIBUTION TRUCK; FUEL TRUCK DRIVER; WATER TRUCK - 2 AXLE; DUMP TRUCK, LESS THAN 16 YDS. WATER LEVEL; EROSION CONTROL DRIVER WORK ON ALL MILITARY BASES:
- Base rate
- $41.87
- Fringe
- $35.69
- Base + fringe
- $77.56
TEAM0011-002 · Union rate · effective 2025-07-01
PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB]
TRUCK DRIVER GROUP 4 DRIVER OF TRANSIT MIX TRUCK, UNDER 3 YDS.; DUMPCRETE TRUCK, LESS THAN 6-1/2 YDS. WATER LEVEL WORK ON ALL MILITARY BASES:
- Base rate
- $42.06
- Fringe
- $35.69
- Base + fringe
- $77.75
TEAM0011-002 · Union rate · effective 2025-07-01
PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB]
TRUCK DRIVER GROUP 5 WATER TRUCK, 3 OR MORE AXLES; TRUCK GREASER AND TIRE PERSON ($0.50 ADDITIONAL FOR TIRE PERSON); PIPELINE AND UTILITY WORKING TRUCK DRIVER, INCLUDING WINCH TRUCK AND PLASTIC FUSION, LIMITED TO PIPELINE AND UTILITY WORK; SLURRY TRUCK DRIVER WORK ON ALL MILITARY BASES:
- Base rate
- $42.09
- Fringe
- $35.69
- Base + fringe
- $77.78
TEAM0011-002 · Union rate · effective 2025-07-01
PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB]
TRUCK DRIVER GROUP 6 TRANSIT MIX TRUCK, 3 YDS. OR MORE; DUMPCRETE TRUCK, 6-1/2 YDS. WATER LEVEL AND OVER; VEHICLE OR COMBINATION OF VEHICLES - 4 OR MORE AXLES; OIL SPREADER TRUCK; DUMP TRUCK, 16 YDS. TO 25 YDS. WATER LEVEL WORK ON ALL MILITARY BASES:
- Base rate
- $42.12
- Fringe
- $35.69
- Base + fringe
- $77.81
TEAM0011-002 · Union rate · effective 2025-07-01
PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB]
TRUCK DRIVER GROUP 7 A FRAME, SWEDISH CRANE OR SIMILAR; FORKLIFT DRIVER; ROSS CARRIER DRIVER. WORK ON ALL MILITARY BASES:
- Base rate
- $42.37
- Fringe
- $35.69
- Base + fringe
- $78.06
TEAM0011-002 · Union rate · effective 2025-07-01
PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB]
TRUCK DRIVER GROUP 8 DUMP TRUCK, 25 YDS. TO 49 YDS. WATER LEVEL; TRUCK REPAIR PERSON; WATER PULL - SINGLE ENGINE; WELDER WORK ON ALL MILITARY BASES:
- Base rate
- $42.62
- Fringe
- $35.69
- Base + fringe
- $78.31
TEAM0011-002 · Union rate · effective 2025-07-01
PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB]
TRUCK DRIVER GROUP 9 TRUCK REPAIR PERSON/WELDER; LOW BED DRIVER, 9 AXLES OR OVER WORK ON ALL MILITARY BASES:
- Base rate
- $42.82
- Fringe
- $35.69
- Base + fringe
- $78.51
TEAM0011-002 · Union rate · effective 2025-07-01
PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB]
TRUCK DRIVER GROUP 10 DUMP TRUCK - 50 YDS. OR MORE WATER LEVEL; WATER PULL - SINGLE ENGINE WITH ATTACHMENT WORK ON ALL MILITARY BASES:
- Base rate
- $43.12
- Fringe
- $35.69
- Base + fringe
- $78.81
TEAM0011-002 · Union rate · effective 2025-07-01
PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB]
TRUCK DRIVER GROUP 11 WATER PULL - TWIN ENGINE; WATER PULL - TWIN ENGINE WITH ATTACHMENTS; WINCH TRUCK DRIVER - $1.25 ADDITIONAL WHEN OPERATING WINCH OR SIMILAR SPECIAL ATTACHMENTS WORK ON ALL MILITARY BASES:
- Base rate
- $43.62
- Fringe
- $35.69
- Base + fringe
- $79.31
TEAM0011-002 · Union rate · effective 2025-07-01
PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB]
TRUCK DRIVER GROUP 12 BOOM TRUCK 17K AND ABOVE WORK ON ALL MILITARY BASES:
- Base rate
- $44.05
- Fringe
- $35.69
- Base + fringe
- $79.74
TEAM0011-002 · Union rate · effective 2025-07-01
PREMIUM PAY: $3.00 PER HOUR ADDITIONAL. [29 PALMS MARINE BASE, CAMP ROBERTS, CHINA LAKE, EDWARDS AFB, EL CENTRO NAVAL FACILITY, FORT IRWIN, MARINE CORPS LOGISTICS BASE AT NEBO & YERMO, MOUNTAIN WARFARE TRAINING CENTER, BRIDGEPORT, POINT ARGUELLO, POINT CONCEPTION, VANDENBERG AFB]
Full determination, counties covered, and modification history for CA20260022
A classification that is not printed on the determination is not priced by it. The published route for adding one is a conformance request to the contracting officer, not an estimate.
Price the classifications you are bidding
Pick the determination, tick the classifications you carry, enter your hours, and get a dated basis document: the determination number, the modification number, the publication date, the counties covered, the premium-pay footnotes attached to each classification you priced, and the extended cost at your hours.
This page covers federal Davis-Bacon general wage determinations only. State prevailing-wage programmes and Service Contract Act determinations are published separately and are not included here.
The Department of Labor republishes determinations under new modification numbers. This page shows the modification named above; check the source before relying on these rates in a bid.
Which determination, construction type, and classification apply to a particular contract depends on facts specific to that contract. This page states what the published determination says; confirm applicability with your contracting officer.